Update for MWRA Northern Intermediate High
Project in Stoneham
(MWRA Contract 7067)

About this Project:

The Northern Intermediate High Project will provide water system redundancy to MWRA's Northern Immediate High service area, which serves the fully-supplied communities of Reading and Stoneham and to the partially-supplied communities of Wakefield, Wilmington, Winchester, and Woburn.

MWRA supplies water to the Northern Intermediate High service communities through a single transmission main: Section 89. Because there is currently no fully-redundant pipeline for Section 89, it can not be taken out of service for inspection and repairs. The potential loss of Section 89 would result in a rapid loss of service in Reading, Stoneham and Woburn, and possible water restrictions in Wakefield, Wilmington and Winchester.

MWRA is installing a total of 36,000 linear feet of new water main varying in diameter from 12-in to 48-inch (Sections 110 and 112) and appurtenances such as valves, that will provide water system redundancy and allow MWRA to take Section 89 out of service for inspection and rehabilitation.

This work is to be performed through four construction contracts. The first contract was completed in May 2015.  The overall project is expected to be complete in June 2019.

For more information, please contact Jeff McLaughlin at (617) 305-5762.

Work in Stoneham:

Under Contract 7067, MWRA contractors will install 13,200 linear feet of 48-inch diameter water main (Section 110) in Stoneham.

This work is expected to commence July 2016 and be complete in June, 2019.

For more information, please contact Jeff McLaughlin at (617) 305-5762.

Updates

May 4, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Updated Work Schedule:

  • 48-inch main on Wright Street
  • Pre-drilling for ledge on Main Street
  • 48-inch main along DCR roadway
progress photo

48-inch water main installation on DCR roadway

progress photo

48-inch water main installation on Wright Street

progress photo

Pre drilling ledge on Main Street

April 20, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Updated Work Schedule:

  • Stoneham water main on Montvale Ave
  • Pre-drilling for ledge on Main Street
  • Mobilize to Gillis Pump Station

Montvale Avenue Water Main Installation

Montvale Avenue Traffic Detour

Main Street ­ Pre Drilling Edge

If you have any questions please do not hesitate to call or email us. MWRA Contacts: Jeffrey McLaughlin (617) 305-5762 or on site: Alejandro Alvarez (617) 454-7531.

March 14, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Update: Montvale Avenue at Wright and Cottage Streets, Stoneham Rescheduled

The temporary closure of Montvale Avenue has been rescheduled due to weather. Work is now scheduled to take place Monday March 19, 2018. Updated info below.

MWRA is installing a new pipeline through the Town of Stoneham for additional water supply redundancy. To accomplish this work the pipe will need to cross several major roadways, including Montvale Ave. For safety reasons, it is necessary to temporarily close a portion of Montvale Ave. between 8:00AM and 4:00PM starting Monday March 19, 2018. Montvale Ave. will be closed at the intersection of Cottage and Wright Streets. Pipeline construction at this location will take approximately one week to complete.

During the closure of this section of Montvale Ave., it is necessary to detour traffic to adjacent roads in accordance with the attached plan using Lindenwood Road (orange dotted line) for vehicles.

Montvale Ave Detour

Traffic detour signage will be in place as well as additional police officers to assist with the detour. Please allow extra time for your commute. Please note if you are a patient of a medical facility or a customer of a business within the detoured area please inform the detail police officer and they will allow you to proceed to your destination.

MWRA has recently implemented a new notification system called Everbridge for communicating information to residents regarding construction projects, community meetings and more. Once you sign up you will receive periodic updates on the progress of the construction project. We encourage all anyone interested in this project to sign up at
http://www.mwra.com/updates/everbridge/join.html.

The name of this project is the Northern Intermediate High (NIH), Stoneham.

We apologize for any inconvenience encountered as a result of this project. If you have
any questions please do not hesitate to call or email us. MWRA Contacts: Jeffrey McLaughlin (617) 305-5762 or on site: Alejandro Alvarez (617) 454-7531.

March 12, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Update: Montvale Avenue at Wright and Cottage Streets, Stoneham Rescheduled

The temporary closure of Montvale Avenue has been rescheduled. Work is now scheduled to take place Wednesday March 14, 2018. Updated info below.

MWRA is installing a new pipeline through the Town of Stoneham for additional water supply redundancy. To accomplish this work the pipe will need to cross several major roadways, including Montvale Ave. For safety reasons, it is necessary to temporarily close a portion of Montvale Ave. between 8:00AM and 4:00PM starting Wednesday March 14, 2018. Montvale Ave. will be closed at the intersection of Cottage and Wright Streets. Pipeline construction at this location will take approximately one week to complete.

During the closure of this section of Montvale Ave., it is necessary to detour traffic to adjacent roads in accordance with the attached plan using Lindenwood Road (orange dotted line) for vehicles.

Montvale Ave Detour

Traffic detour signage will be in place as well as additional police officers to assist with the detour. Please allow extra time for your commute. Please note if you are a patient of a medical facility or a customer of a business within the detoured area please inform the detail police officer and they will allow you to proceed to your destination.

MWRA has recently implemented a new notification system called Everbridge for communicating information to residents regarding construction projects, community meetings and more. Once you sign up you will receive periodic updates on the progress of the construction project. We encourage all anyone interested in this project to sign up at
http://www.mwra.com/updates/everbridge/join.html.

The name of this project is the Northern Intermediate High (NIH), Stoneham.

We apologize for any inconvenience encountered as a result of this project. If you have
any questions please do not hesitate to call or email us. MWRA Contacts: Jeffrey McLaughlin (617) 305-5762 or on site: Alejandro Alvarez (617) 454-7531.

March 8, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Important Public Notice: Montvale Avenue at Wright and Cottage Streets, Stoneham

A reminder that a temporary closure of Montvale Avenue has been scheduled for Monday, March 12, 2018. Updated information below.

MWRA is installing a new pipeline through the Town of Stoneham for additional water supply redundancy. To accomplish this work the pipe will need to cross several major roadways, including Montvale Ave.

For safety reasons, it is necessary to temporarily close a portion of Montvale Ave. between 8:00AM and 4:00PM starting Monday March 12, 2018. Montvale Ave. will be closed at the intersection of Cottage and Wright Streets. Pipeline construction at this location will take approximately one week to complete.

During the closure of this section of Montvale Ave., it is necessary to detour traffic to adjacent roads in accordance with the attached plan using Lindenwood Road (orange dotted line) for vehicles.

Montvale Ave Detour

Traffic detour signage will be in place as well as additional police officers to assist with the detour. Please allow extra time for your commute. Please note if you are a patient of a medical facility or a customer of a business within the detoured area please inform the detail police officer and they will allow you to proceed to your destination.

MWRA has recently implemented a new notification system called Everbridge for communicating information to residents regarding construction projects, community meetings and more. Once you sign up you will receive periodic updates on the progress of the construction project. We encourage all anyone interested in this project to sign up at
http://www.mwra.com/updates/everbridge/join.html.

The name of this project is the Northern Intermediate High (NIH), Stoneham.

We apologize for any inconvenience encountered as a result of this project. If you have
any questions please do not hesitate to call or email us. MWRA Contacts: Jeffrey McLaughlin (617) 305-5762 or on site: Alejandro Alvarez (617) 454-7531.

March 6, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

A reminder that a temporary closure of Montvale Avenue has been scheduled for Monday, March 12, 2018.

Construction Update

Work underway:

  • Stoneham water main on Cottage Street
  • Pre-drilling for ledge on Main Street
  • Mobilize to Gillis Pump Station
  • Submittals

Construction Photos

image 1 030618

Installation of 48-inch pipe at Cottage Street

image 2 030618

Water main, Cottage Street

February 15, 2018

Construction Photos

Sign up for electronic project notifications and updates through our Everbridge service.

Layout, Gillis Pump Station

Layout, Gillis Pump Station

Water main, Cottage Street

Water main, Cottage Street

For more information, please contact Jeff McLaughlin at (617) 305-5762.

April 7, 2017

Dear Residents,

A reminder that the MWRA will hold a public meeting on the MWRA Section 110 Northern Intermediate High Project (MWRA Contract 7067) in Stoneham:

Thursday, April 13, 2017
7:00 PM
Stoneham Town Hall
35 Central Street, Stoneham, MA

The Massachusetts Water Resources Authority recently awarded the Northern Intermediate High (NIH) redundant water main construction contract to Albanese D&S Construction Company.  This project involves the installation of 13,200 feet of a 48 inch water pipeline within the town of Stoneham.  The contract also includes the installation of new water valves and new meters.  Albanese D&S plans on performing the work in phases.

The first phase of work will begin the week of April 10, 2017.  This phase of work involves the installation of a temporary water bypass system.  The bypass system will be in place until late fall of 2017.  Once this first phase of work is complete then the contractor will begin to install the 48 inch water line.  The current area of work will take place on Cottage Street between Lindenwood Road and Williams Street.  Work hours will be from Monday through Friday from 7AM-4PM. 

The MWRA has met with Stoneham’s’ DPW office, Police and Fire Departments, and other offices to review the construction plans, traffic plans, police detail plans, and other important information to insure the project advances with everyone’s cooperation.   

As mentioned you will begin to see this construction activity beginning the  week of April 10th.  Construction activity will increase as the weather improves.  For more information on the project please visit the MWRA.com web site and search for The Northern Intermediate High (NIH) project.  If you have any questions kindly contact MWRA’s community relations manager Jeff McLaughlin at 617-305-5762 or you may email him at Jeffrey.McLaughlin@mwra.com.

MWRA has recently developed a new notification system for communicating information to residents regarding construction projects, community meetings and more.  Once you sign up you will receive periodic updates on the progress of the construction project.  We encourage all residents to sign up at http://www.mwra.com/updates/everbridge/join.html.

April 5, 2017

The Massachusetts Water Resources Authority invites you to attend a public meeting on the MWRA Section 110 Northern Intermediate High Project (MWRA Contract 7067) in Stoneham:

Thursday, April 13, 2017
7:00 PM
Stoneham Town Hall
35 Central Street, Stoneham, MA

To receive electronic project updates please register your email address with the MWRA Alerts Service, provided through Everbridge.

If you have any questions kindly email Jeff McLaughlin or call (617) 305-5762.

April 1, 2016

We will post project updates in this section.

To receive electronic project updates please register your email address with the MWRA Alerts Service, provided through Everbridge.

If you have any questions kindly email Jeff McLaughlin or call (617) 305-5762.

About the Northern Intermediate High Project

MWRA Contract 7067 in Stoneham is part of MWRA's Northern Intermediate High Project, which is broken down into four separate construction contracts with different locations:

  • Contract 7067: the construction of 13,200 linear feet of 48-inch diameter transmission main in Stoneham. Construction of this contact is expected to begin in July 2016 and be completed by June 2019. Details and updates are on this page.

  • Contract 7066: the construction of 2,400 linear feet of 36-inch water transmission main in Reading, coordinated with the MassDOT road reconstruction project on West Street.  This contract was completed in May 2015.

  • Contract 7471 (Section 110):  the construction of 8,800 linear feet of 36-inch water transmission main Woburn and Reading. Work began on March 28, 2016 and is expected to be complete in December, 2017.

  • Contract 7478: the construction of 7,800 linear feet of 48-inch diameter transmission main in Stoneham and 3,000 linear feet of 16-inch and 12-inch diameter transmission main to serve new Wakefield Meter 96. Construction of this contact is expected to begin in May 2016 and be completed by December 2017.


For more information, please contact Jeff McLaughlin at (617) 305-5762.