Return to mwra.com home
Massachusetts Water Resources Authority
PROJECT UPDATE
DATE:
Updated December 23, 2011
First Post August 25, 2011
CONTACT:

Tom Lindberg, MWRA Public Affairs
(617) 660-7974, Tom.Lindberg@mwra.state.ma.us

Ria Convery, Communications Director
(617) 788-1105, Ria.Convery@mwra.state.ma.us

MWRA to Begin Work on Project to Provide
Emergency Back­up Water Service to Reading

MORE INFORMATION

mwra paving crew

Paving crew 12/23/11

map of controlled blasting areas
Map of Controlled Blasting Areas
Larger Image | PDF
reading stoneham project map
Project Map
Larger Image | PDF
Public Meetings
Public Meeting in Reading on 09/26/11
Public Meeting in Stoneham on 09/28/11

Project Update (12/23/11)

  • MWRA’s contractor has finished installing all the 36-inch water line and heavy construction activities have now been completed. The streets will be swept and the area secured.
     
  • Through January, the contractor will be inspecting, filling, testing, and disinfecting the new line. These activities requiring both day and nighttime work, but generate significantly less noise.
     
  • In the spring, the contractor will return to construct new pedestrian ramps and sidewalks along the Stonehill Towers side of Route 28 during daytime hours.  Final paving (curb to curb) along the southbound side of Route 28 from North Street in Stoneham up to South Street in Reading will be done at night.
     
    MWRA thanks residents for their patience and understanding during this project.

All updates for this project


About Northern Intermediate High, Stoneham-Reading Connection Project

In September 2011, MWRA’s contractor, Albanese D&S of Dracut, Massachusetts, will begin work to install 2,200 linear feet of 36-inch diameter water main in Reading. Work will start at South Street and continue under Route 128 along Main Street to the intersection of North Street in Stoneham. Most work will be complete by December 2012.

The new pipeline, which will connect Reading’s water system and that of Stoneham, will provide back-up water service to Reading in case of an emergency.  

The back-up water main is being installed in preparation for an upcoming MWRA pipeline project to improve water service for Stoneham, Reading, Woburn, Wakefield, Wilmington and Winchester.

Traffic Impacts

Pipe installation will take place on the southbound side of Main Street/Route 28. Because this is a very busy roadway, most of the work will be performed during nighttime hours (9PM – 5AM), as required by the Massachusetts Department of Transportation, which has jurisdiction over this section of the roadway.  Additional allowable daytime work will occur between the hours of 10AM and 3PM. Traffic detours, signage and police details will be in place so that the traveling public will be able to get around the construction site safely. Access for all local residences and businesses will be maintained.

Safety

Subsurface investigations show that that controlled rock blasting and minimal mechanical rock removal will likely be necessary; therefore, all structures within 500 feet of a rock removal area will receive a pre-blast survey. 

Upcoming Meetings

MWRA will meet with municipal officials in Stoneham and Reading to confirm the details and schedule of this important project. A public meeting will then be held to describe the scope and schedule of the work, including the sequence of traffic detours and the blasting and safety protocol required before construction commences.

For more information about the project please contact: Tom Lindberg/ MWRA at 617.660.7974 or by email: Tom.Lindberg@mwra.state.ma.us

###

Back to top

Updated December 27, 2011

Posted August 25, 2011