Return to mwra.com home
Massachusetts Water Resources Authority
FOR IMMEDIATE RELEASE
DATE:
March 31, 2011
Updated September 2, 2011
CONTACT:

Ria Convery, Communications Director
(617) 788-1105, <ria.convery@mwra.state.ma.us>

MWRA PIPELINE WORK TO BEGIN IN LOWER MILLS, DORCHESTER

Construction work on MWRA's Southern Spine Section 107 Phase 2 will begin in the Lower Mills section of Dorchester (Boston) on April 18, 2011.

PROJECT OVERVIEW

MWRA's Southern Spine Distribution Mains are the major water distribution pipelines for Milton, Quincy and the Southeast corner of Boston. Parts of the Southern Spine were built in the early 1900s. Some sections are very old and unlined; they have been functioning at only 50% of their original carrying capacity for years because of tuberculation (rust build-up and pocking) along the pipeline walls.

This project is being constructed in five phases, with the first three completed. It includes connections to MWRA's new Blue Hills Covered Storage Facility and the rehabilitation of more than 12 miles of water mains, valves and meters.

The Southern Spine Project will greatly increase the pipeline's delivery capacity. It will also extend its overall life span by at least 50 years and provide much-needed system redundancy for its service communities in the event of a major water main break upstream.

THIS SEGMENT

On December 16, 2009, MWRA awarded the Southern Spine 107 Phase 2 Project to RJV Construction Corp., Inc. The $14.5 million project includes the replacement of 1.7 miles of 48-inch diameter water main and the relining of an additional 4,000 feet of pipe.

Construction began in February 2010 along Adams Street in East Milton Square. The next phase of work will begin on April 18, 2011 in the Lower Mills section of Boston.

TRAFFIC IMPACTS

This work will require periodic road closures/diversions on Washington Street, Adams Street and River Street between April and November. (See construction update map for current schedule.)

If you have any questions or concerns about this project, please contact Jeffrey McLaughlin, MWRA Public Affairs (617) 660-7976.

Regular updates will be posted on mwra.com.

 

Construction Activity
in Lower Mills, Dorchester

Updated September 2, 2011

Road Closure Notice - Washington Street from Dorchester Avenue/Adams Street to River Street in Dorchester will closed at 7AM on Tuesday, September 6, 2011. It will reopen in the afternoon or early evening of Thursday, September 8. The road closure is necessary to allow contractors to perform installation of pipes, interconnections and valves. It is likely that a similar road closure will occur again, during the week of September 12. We will keep you updated on the potential road closure as work progresses.

Project Update - Pipe installation along Washington Street progressed well this week. The contractor encountered less ledge and rock than expected. The contractor will need to revisit the site at Dunkin Donuts to reassemble and hand-finish the pipe with concrete. Similar work will also take place at Richmond and Washington Street. Enjoy your Labor Day weekend.

Rolling Update / Archive

Project Map project map - lower mills
Short Term Parking

(Updated April 21, 2011)

Shaws and CVS will allow short term parking for customers of Lower Mills shopping area. Shaws will allow short term parking in the below-ground garage and CVS will allow parking within the side/back lot.

Mr. Dolan from Dolans Funeral Home has also offered short term parking during times when it will not interfere with wakes or funerals.
 
The MWRA and its contractor will make up signs indicating these areas are available for short term parking during construction hours.
 
The MWRA would like to thank Shaws, CVS, and Dolans for allowing parking during these times.

Related
About the Southern Spine Distribution Mains Rehab Project
Southern Spine Section 107 Phase I (2007)
Blue Hills Covered Storage Facility
MWRA Contact
Jeffrey McLaughlin,
Public Affairs (617) 660-7976

###

Back to top

Updated September 19, 2011
Posted March 31, 2011

ß